Schedule
Last Content Update:
During construction this page will provide estimated dates of construction (these will be updated periodically – locations are approximate based on nearest cross street). Please refer to "Areas of Work" page for street listings.
- Town has several Projects in process:
- Phase 1D-2A: Route 137 / Morton Road Area (Construction in Progress)
- Crowell Road Phase 2 and Chatham Fish Pier Infrastructure Project: (Construction in Progress)
- Queen Anne Pumping Station Upgrade (Construction in Progress)
- Mill Pond Pumping Station Upgrade - in Design (anticipated construction TBD)
- Phase 1C-5: Cedar Street and Pond View/Kelly Lane/ Woodcarver Knoll in Design (Construction TBD
Phase 1D-2A: Route 137 - Morton Road Sewer Extension Project, Contract No. 2019-CWMP-2
The following roads are included in this Contract:
Meetinghouse Road, Middle Road, Morton Road, Mill Hill Road, Twine Field Drive, and the Bike Path.
CONSTRUCTION ACTIVITY - CONTRACT 1D-2A is scheduled to start Summer 2022 and is anticipated to continue through Spring 2024.
Construction Update:
Pump Station #3 (Meetinghouse Road): Continued pump station work through Summer 2023.
Pump Station #4 (Twine Field Drive): Continued pump station work through Summer 2023.
Meetinghouse Road: Lateral work expected the week of 6/5/2023 - 6/9/2023. Pavement preparation/milling will occur on Thursday, 6/8 with paving on Friday, 6/9. Police detail(s) will be in place to assist motorists. Detour may be in place.
Morton Road: Tentative sewer testing to begin the week of 6/5/2023 through 6/23/2023. Police detail(s) will be in place to assist motorists.
Mill Hill Road: No work planned 5/29/2023 through 6/16/2023.
Middle Road: Tentative sewer testing to begin the week of 6/12/2023 through 6/23/2023.
Twine Field Drive: Sewer work expected to begin the week of 11/14/2022 - 11/18/2022.
Old Colony Rail Trail (Bike Path): No current work planned.
Queen Anne Pumping Station Upgrade, Contract No. 2021-CWMP-1
The following roads are included in this Contract:
Queen Anne Road; Oyster Pond Furlong
CONSTRUCTION ACTIVITY
- Construction is scheduled to start Fall 2022 and is anticipated to continue through to Fall 2023.
Construction Update:
Queen Anne Pumping Station (40 Queen Anne Road; SE corner of Queen Anne Road and Oyster Pond Furlong): Site work is expected to begin at the pump station site the week of 1/25/2023 and continue through the Spring of 2023.
No work planned for the week of 5/22/2023 - 6/23/2023.
Crowell Road Phase 2 and Chatham Fish Pier Infrastructure Project
The following roads are included in this Contract:
Crowell Road, Tip Cart Lane, Barcliff Avenue, Barcliff Avenue Extension, Shore Road
CONSTRUCTION ACTIVITY
Crowell Road Phase 2 and Chatham Fish Pier Construction is scheduled to start Fall 2022 and is anticipated to continue through to Spring 2024.
Construction Update:
Crowell Road/Tip Cart Drive:
Week of 6/12/2023 - 6/16/2023: Tentative - preparation for paving expected on Crowell Road between the intersections of Lake Street and Kendrick Harvest Way.
Week of 6/19/2023 - 6/23/2023: Tentative - paving expected on Crowell Road between the intersections of Lake Street and Kendrick Harvest Way.
Chatham Fish Pier Parking Lot:
Week of 6/5/2023 - 6/9/2023: Preparation for paving is expected Tuesday, 6/6. Police detail(s) will be in place to assist motorists. Detour may be in place.
Week of 6/12/2023 - 6/16/2023: Paving expected on Tuesday, 6/13. Police detail(s) will be in place to assist motorists. Detour may be in place.
Department of Public Works:
Drainage work is expected to continue 4/04/3023 through 4/14/2023.
PHASE 1D-1: CONTRACT NO. 2018-CWMP-4: CHATHAM/HARWICH CONNECTION PROJECT
The following roads are included in this contract:
Old Queen Anne Road; Meetinghouse Road; Duncan Lane; Mallard Road; Partridge Path; Middle Road
CONSTRUCTION ACTIVITY - CONTRACT 1D-1 began in the Fall of 2019 and is anticipated to continue through Spring 2021.
Construction Area 17 (All Roads) 1D-1:
Fall 2019
Construction has concluded for all roads under this project including:
- Meetinghouse Road, Old Queen Anne Road, Middle Road, Duncan Lane, Partridge Path, Mallard Road, and Sam Ryder Road
Construction Area 18 (Meetinghouse Road) 1D-1:
Fall 2019 - Winter 2020
Pumping Station No. 6 at 601 Meetinghouse Road
Road will remain open. Possible alternating traffic for select times.
- Currently under construction, delays may occur on Meetinghouse Road as materials are delivered to site.
PHASE 1C-3&4: CONTRACT NO. 2018-CWMP-2
The following roads are included in this contract:
Balfour Lane; Barbara Drive; Bay View Street; Captain Richards Way; Carolyn Drive; Christopher Hardings Lane; Cynthia Drive; Ell Street; Ellis Street; Ethelma Drive; Heritage Lane; Jeanette Drive; Jeanette Road; Lime Hill Road; Linden Tree Lane; Perch Pond Road; Sky Way; Smith Street; Snow Lane; Uncle Alberts Drive; Vineyard Avenue; Waveland Avenue; White Pond Road; Wilfred Road
CONSTRUCTION ACTIVITY - CONTRACT 1C-3&4 is scheduled to start September 2019 and is anticipated to continue through Spring 2021.
Construction Area 1 (Ethelma Drive)
Fall 2019 - Spring 2021
Sewer Construction is currently planned to begin the week of 11/18/19 and continue through 1/24/2020. Gravity sewer lateral work is planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020. Please note that watermain and services work is also expected in this area.
Sewer testing is planned to begin 4/13/2020 and continue through to 5/01/2020 in this area.
Road work is expected to begin 10/28/2020 and continue through to 11/20/2020. Road work will include lowering manhole covers and pavement preparation/installation on Ethelma, Barbara, and Carolyn Drives neighborhoods.
Paving planned to begin in this area on 5/03/2021.
Estimated Schedule includes:
- Gravity sewer installation 11/2019 - 12/2019
- Gravity sewer laterals 12/2019 - 1/2020
- Final Paving estimated 5/2021
Construction Area 2 (Barbara Drive)
Fall 2019 - Spring 2021
Construction is currently planned to begin the week of 11/18/19 and continue through 1/24/2020. Gravity sewer lateral work is planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020. Please note that watermain and services work is also expected in this area.
Sewer testing is planned to begin 4/13/2020 and continue through to 5/08/2020 in this area.
Road work is expected to begin 10/28/2020 and continue through to 11/20/2020. Road work will include lowering manhole covers and pavement preparation/installation on Ethelma, Barbara, and Carolyn Drives neighborhoods.
Paving planned to begin in this area on 5/03/2021.
Estimated Schedule includes:
- Gravity sewer installation 11/2019 - 12/2019
- Gravity sewer laterals 12/2019 - 1/2020
- Final Paving estimated 5/2021
Construction Area 3 (Carolyn Drive)
Fall 2019 - Spring 2021
Construction is currently planned to begin the week of 11/18/19 and continue through 12/13/19. Gravity sewer main installation and laterals is planned to resume the week of 1/20/2020 and continue through to 3/13/2020. Cleanup of this area is expected for the week of 3/09/2020 once lateral work is complete. Please note that watermain and services work is also expected in this area.
Sewer testing is planned to begin 4/13/2020 and continue through to 5/08/2020 in this area.
Road work is expected to begin 10/28/2020 and continue through to 11/20/2020. Road work will include lowering manhole covers and pavement preparation/installation on Ethelma, Barbara, and Carolyn Drives neighborhoods.
Paving planned to begin in this area on 5/03/2021.
Estimated Schedule includes:
- Gravity sewer installation 11/2019 - 2/2020
- Gravity sewer laterals 12/2019 - 3/2020
- Final Paving estimated 5/2021
Construction Area 4 (Jeanette Drive & Jeanette Road)
Fall 2019 - Spring 2021
Jeanette Drive: Construction is currently planned to begin the week of 11/18/19 and continue through 12/27/19. Gravity sewer lateral work is planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020. Please note that watermain and services work is also expected in this area.
Sewer testing is expected to begin 05/04/2020 and continue through to 05/08/2020 in this area.
Road work is expected to begin 11/23/2020 and continue through to 12/11/2020. Road work will include pavement preparation on Jeanette Drive area.
Jeanette Road: Construction of the gravity sewer is currently planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020. Please note that watermain and services work is also expected in this area.
Road work is expected to begin 10/28/2020 and continue through to 12/11/2020. Road work will include pavement preparation on Perch Pond Road/Jeanette Road areas.
Jeanette Drive/Road: Testing of the sewer main to be started the week of 2/1/2021 in this area, and continue intermittently through 2/26/2021.
Paving planned in the Jeanette Drive area on 5/03/2021.
Estimated Schedule includes:
Jeanette Drive:
- Gravity sewer installation 11/2019 - 12/2019
- Gravity sewer laterals 12/2019 - 1/2020
- Final Paving estimated 5/2021
Jeanette Road:
- Gravity sewer installation 1/2020 - 1/2020
- Gravity sewer laterals 12/2019 - 2/2020
- Final Paving estimated 4/2021
Construction Area 5 (Wilfred Road and Cynthia Drive/Wilfred Road Odor Control Site)
Fall 2018 - Spring 2021
Construction is currently planned to begin the week of 12/09/19 and continue through 1/10/2020 for low pressure sewer main and lateral installation on Wilfred Road. Gravity Sewer Installation is planned to begin the week of 1/27/2020 and continue through to 2/28/2020; with watermain work near the intersection of Wilfred Road and Jeanette Road/Drive.
Work at the odor control site on Wilfred Road will occur intermittently through October 2021.
Paving, roadway cleanup and site restoration planned for the weeks of 5/10/2021, 5/17/2021 and 5/24/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Road milling/pavement preparation is planned in this area beginning the week of 5/03/2021.
Hydroseeding planned for this area the week on 6/7/2021.
Estimated Schedule includes:
- Test Pits 9/2019
- Force main installation 10/2019
- Relocate existing water main - 2/2020
- Gravity sewer installation 1/2020 - 2/2020
- Low pressure sewer installation 12/2019 - 2/2020
- Sewer laterals 12/2019 - 02/2020
- Final Paving estimated 5/2021
Wilfred Road Odor Control Site:
- Construction 12/2020 - 10/2021
Construction Area 6 (Balfour Lane/Balfour Lane Pumping Station)
Fall 2019 - Spring 2021 (Roadword) / Winter 2019 - Spring 2021 (Pumping Station Work)
Construction is planned to begin 1/29/2020 for mobilization and to begin Gravity Sewer Installation through 1/31/2020. Work is then expected to continue starting the week of 2/10/2020 through 3/20/2020 for Gravity Sewer Work, Service Laterals, and Force Main Work. Electrical work by an Eversource contractor is expected to begin the week of 9/14/2020 and last approximately 4 weeks.
Pump station work is estimated to begin the week of 4/27/2020 and continue intermittently through October 2021.
Road work is expected to begin 11/09/2020 continuing through to 11/25/2020. Road work will include lowering manhole covers and pavement preparation/installation on Balfour Lane.
Paving planned for this area the week of 5/17/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Estimated Schedule includes:
- Gravity sewer and force main installation 12/2019 - 3/2020
- Gravity sewer laterals 2/2020 - 3/2020
- Force Main installation - 1/2020 - 3/2020
- Final Paving estimated 5/2021
Balfour Lane Pumping Station:
- Construction 02/2021 - 10/2021
Construction Area 7 (Perch Pond Road/Perch Pond Road Pumping Station)
Fall 2020 - Spring 2021
Construction for the installation of gravity sewer is tentatively planned to begin the week of 12/30/19 and continue through 1/24/20. Gravity sewer lateral work is planned for the week of 1/20/2020 and continue through to 1/31/2020. Force Main/Low Pressure Sewer Installation will continue through 2/7/2020.
Sewer testing is expected to begin in this area 05/04/2020 and continue through to 05/22/2020.
Pump station work is estimated to begin the week of 05/18/2020 and continue intermittently through October 2021.
Pavement preparation for full width road reconstruction planned for 4/12/2021 with paving planned to follow on 4/13/2021.
Road work is expected to begin 10/28/2020 and continue through to 12/11/2020. Road work will include pavement preparation on Perch Pond Road/Jeanette Road areas.
Testing of the sewer main to be started the week of 1/18/2021 and continue intermittently through 2/26/2021.
Estimated Schedule includes:
- Test Pits 9/2019
- Gravity sewer and force main installation 12/2019 - 2/2020
- Low pressure sewer installation 12/2019 - 2/2020
- Gravity sewer and low pressure laterals 1/2020 - 2/2020
- Final Paving estimated 4/12/2021 - 4/13/2021
Perch Pond Pumping Station:
- Construction 04/2021 - 10/2021
Construction Area 8 (Heritage Lane)
Winter 2020 - Spring 2021
Construction for the installation of gravity sewer and service laterals is tentatively planned to begin the week of 3/16/2020 and continue through 5/08/2020.
Testing of the sewer main to be started the week of 1/18/2021 and to continue through the week of 1/29/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Sewer work and testing planned for the week of 4/05/2021 in this area.
Hydroseeding planned for this area the week on 6/7/2021.
Estimated Schedule includes:
- Gravity sewer and installation 2/2020 - 5/2020
- Gravity sewer laterals 2/2020 - 5/2020
- Final Paving estimated TBD
Construction Area 9 (Sky Way and Ell Street/Sky Way Pumping Station)
Fall 2019 - Spring 2021 (Roadwork) / Fall 2019 - Spring 2021 (Pumping Station Work)
Construction is planned to continue through 12/13/19.
Sewer testing is planned to begin 4/06/2020 and continue through to 4/17/2020 in this area.
Pump station work is estimated to begin the week of 4/27/2020 and continue intermittently through October 2021.
Paving, roadway cleanup and site restoration planned for the weeks of 5/10/2021, 5/17/2021, and 5/24/2021.
Milling and pavement preparation is planned in this area beginning 5/03/2021.
Hydroseeding planned for this area the week on 6/7/2021.
Estimated Schedule includes:
- Gravity sewer and force main installation continues 10/21 through 11/15
- Gravity sewer laterals 11/18/19 - 12/13/19
- Final Paving estimated 5/2021
Sky Way Pumping Station:
- Construction 4/2020 - 10/2021
Construction Area 10 (White Pond Road)
Winter 2019 - Spring 2021
Low pressure sewer work is expected the week of 4/13/2020 and continuing through 4/24/2020. Gravity sewer work is expected to begin the week of 6/15/2020 and continue through to 6/26/2020.
Staging of equipment and materials within the road right-of-way is likely for this area.
Sewer testing expected to begin in this area the week of 3/01/2021
Pavement preparation for full width paving planned for 4/12/2021 - 4/14/2021.
Paving planned in this area the week of 5/17/2021.
Estimated Schedule includes:
- Gravity sewer and low pressure sewer installation 4/2020 - 6/2020
- Gravity sewer and low pressure laterals 4/2020 - 6/2020
- Final Paving estimated 4/2021 - 5/2021
Construction Area 11 (Lime Hill Road and Christopher Harding Lane)
Winter 2019 - Spring 2021
Work is planned to commence on 2/3/2020 and continue through 3/27/2020 for Gravity, Force Main, Low Pressure Sewer and Lateral Installation.
Sewer testing is planned 4/19/2021 - 5/07/2021 in this area. Road preparation for paving is planned to begin the week of 4/19/2021. Road paving schedule to be determined the week of 4/26/2021.
Paving, roadway cleanup and site restoration planned for this area the week of 5/17/2021.
Hydroseeding planned for this area the week on 6/7/2021.
Estimated Schedule includes:
- Test Pits to located existing utilities 12/2019
- Gravity sewer and low pressure sewer installation 1/2020 - 4/2020
- Gravity sewer and low pressure laterals 3/2020 - 4/2020
- Final Paving estimated 4/2021 - 5/2021
Construction Area 12 (Vineyard Avenue, Waveland Avenue, Smith Street, Ellis Street, Bay View Street)
Winter/Spring 2020 - Spring 2021
Estimated Schedule includes:
Vineyard Ave:
Low pressure sewer work is estimated to begin the week of 3/23/2020 and continue through 4/03/2020. Gravity sewer work is expected to continue 5/25/2020 through to 6/05/2020.
Testing of the sewer main to be started the week of 4/12/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Milling and pavement preparation is planned in this area beginning 5/03/2021.
Paving planned in this area on 5/06/2021.
Roadway cleanup and sewer manhole work the week of 5/10/2021.
Gravity sewer and low pressure sewer installation 3/2020 - 6/2020
Gravity sewer and low pressure laterals 3/2020 - 6/2020
Final Paving estimated 5/2021
Waveland Ave:
Gravity sewer work is expected to begin 5/11/2020 and continue through to 5/22/2020.
Sewer testing expected to begin the week of 3/22/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Milling and pavement preparation is planned in this area beginning 5/03/2021.
Paving planned in this area on 5/06/2021 and the week of 5/10/2021. Roadway cleanup and site restoration planned the week of 5/17/2021.
Gravity sewer installation 5/2020 - 6/2020
Gravity sewer laterals 5/2020 - 6/2020
Final Paving estimated 5/2021
Smith Street:
Gravity sewer and service laterals work is expected to begin 4/20/2020 and continue through 6/05/2020.
Sewer testing expected to begin the week of 4/05/2021.
Road preparation for paving expected to begin the week of 4/19/2021 with paving estimated on 4/21/2021.
Sewer manhole work expected in this area the week of 5/10/2021.
Roadway cleanup and site restoration planned the week of 5/17/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Gravity sewer installation 4/2020 - 5/2020
Gravity sewer laterals 4/2020 - 6/2020
Final Paving estimated 4/19/2021 - 4/23/2021
Ellis Street:
Low pressure sewer work is estimated to begin the week of 4/06/2020 and continue through 4/10/2020. Gravity sewer work is estimated to begin 5/18/2020 and continue through to 5/29/2020.
Sewer testing expected to begin the week of 3/29/2021.
Paving planned in this area on 5/6/2021 and the week of 5/10/2021. Roadway cleanup and site restoration planned the week of 5/17/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Gravity sewer and low pressure sewer installation 4/2020
Gravity sewer and low pressure laterals 4/2020 - 5/2020
Final Paving estimated 4/2021 - 5/2021
Bay View Street:
Low pressure sewer work is estimated to begin the week of 3/16/2020.
Gravity sewer and service laterals work is expected to begin the week of 5/04/2020 and continue through 5/29/2020.
Sewer testing planned for the weeks 4/5/2021 and 4/12/2021.
Road preparation for paving expected to begin the week of 4/19/2021 with paving estimated on 4/21/2021. Sewer testing tentatively scheduled for the week of 4/26/2021 in this area.
Sewer manhole work expected in this area the week of 5/10/2021.
Roadway cleanup and site restoration planned for the week of 5/17/2021.
Staging of equipment and materials within the road right-of-way is likely for this area.
Gravity sewer and low pressure sewer installation 3/2020 - 5/2020
Gravity sewer and low pressure laterals 4/2020 - 6/2020
Final Paving estimated 4/19/2021 - 4/23/2021
Construction Area 13 (Captain Richards Way)
Spring 2020 - Spring 2021
Low pressure sewer work is estimated to begin the week of 4/06/2020 and continue through 4/17/2020. Gravity sewer work is expected to begin the week of 6/01/2020 and continue through to 6/19/2020. Paving is planned for the week of 6/22/2020.
Paving planned for this area the week of 5/17/2021 with roadway cleanup and site restoration to follow.
Staging of equipment and materials within the road right-of-way is likely for this area.
Sewer testing expected to resume the week of 3/22/2021.
Estimated Schedule includes:
- Gravity sewer and low pressure sewer installation 4/2020 - 6/2020
- Gravity sewer and low pressure laterals 4/2020 - 6/2020
- Final Paving estimated 4/2021 - 5/2021
Construction Area 14 (Linden Tree Lane)
Winter 2020 - Spring 2021
Work is planned to commence on 2/3/2020 and continue through 3/06/2020 for Gravity Sewer, Low Pressure Sewer Installation, and Service Laterals.
Sewer testing is planned to begin in this area 4/19/2021 - 4/23/2021. Preparation for full width road reconstruction expected the week of 5/03/2021, paving schedule to be determined.
Paving planned the week of 5/17/2021 with roadway cleanup and site restoration to follow during that week and into the week of 5/24/2021.
Hydroseeding planned for this area the week on 6/7/2021.
Estimated Schedule includes:
- Gravity sewer and low pressure sewer installation 2/2020 - 3/2020
- Gravity sewer and low pressure laterals 2/2020 - 3/2020
- Final Paving estimated TBD
Construction Area 15 (Snow Lane)
Fall 2020 - Spring 2021
Estimated Schedule includes:
- Water main work 2/2021 - 3/2021
- Gravity sewer and low pressure sewer installation 2/2021 - 4/2021
- Gravity sewer and low pressure laterals 2/2021 - 4/2021
- Full width binder paving on 4/02/2021; final paving TBD in fall 2021.
- Sewer work and sewer lateral work to continue through 4/2/2021. Paving, miscellaneous road work, and clean up is expected the week of 4/5/2021. Please note paving will not occur until sewer installation is complete on this roadway.
- Sewer testing scheduled on this road the week of 5/03/2021 and 5/10/2021. Sewer manhole work is also expected in this area during the week of 5/10/2021.
Construction Area 16 (Uncle Alberts Drive)
Fall 2019 - Spring 2021
- Low pressure sewer installation for 10/2019 - 11/2019
- Low pressure laterals 11/2019 - 12/2019
- Final Paving estimated for 4/2021 - 5/2021
- Sewer testing expected to begin in this area the weeks of 4/12/2021 and 4/19/2021
- Paving planned the week of 5/17/2021 with roadway cleanup and site restoration to follow the week of 5/24/2021.
- Hydroseeding planned for this area the week on 6/7/2021.
PHASE 1E: CONTRACT NO. 2019-CWMP-3: STONY HILL/CROWELL ROAD INFRASTRUCTURE PROJECT
The following roads are included in this contract:
George Ryder Road South; Market Place; Hardings Lane; Crowell Road; Stony Hill Road; Lake Street
CONSTRUCTION ACTIVITY - Phase 1E - (Stony Hill / Crowell Road) began in the Fall 2020 and is scheduled to continue through Fall 2021.
GENERAL INFORMATION ALL CONSTRUCTION CONTRACTS (ONCE CONSTRUCTION BEGINS):
Construction dates are subject to change depending on construction progress and weather conditions. Construction is anticipated to continue through the winter construction season. See Public Notices page for Town issued Press Releases and additional information.
Contractor hours are typically from 7:00 AM to 5:00 PM, weather depending. No work is scheduled for nights, weekends, or holidays. Work may be extended to 7 PM under special circumstances.
When roads/construction areas/zones are closed to thru-traffic, the road will be open to Local Business Traffic and Residents unless otherwise noted. Please follow construction signs as access to/from local businesses and side streets within the construction zones will be construction-dependent and may change during the course of the day or work week. Work may continue in these areas even if not shown in red, and may be performed using alternating traffic.
Construction Area 19 (Stony Hill Road)
Winter 2021 - Summer 2021
Detour routing Stony Hill Road thru traffic via Lake Street to Crowell Road.
Gravity Sewer Installation:
- Construction is complete
Low Pressure Sewer Installation:
- Construction is complete
Stormwater Installation:
- Construction is complete
Testing and Final Paving:
- Testing and final paving are complete. Minor paving modifications will occur.
Construction Area 20 (Crowell Road/Lake Street)
Winter 2021 - Summer 2021
Construction, testing, and final paving are complete
Construction Area 21 (George Ryder South & Market Place)
Fall 2020 - Winter 2021
Final road reconstruction and paving will begin on November 29, 2021. Intermittent delays will occur. Police details will be present to assist traffic
Construction Area 22 (Hardings Lane)
Fall 2020 - Winter 2021
Construction, testing, and final paving are complete
-
Robert Duncanson, Ph.D.
Director